Ellendale Project

SES Brisbane - Ellendale Project
Prev Next
Principle:
Cedar Woods Properties
Contractor:
Shadforth Civil Contractors
Contract Period:
3+ years

PROJECT SCOPE

Ellendale master planned community covers a 227 hectare site with an estimated 980 allotments ranging from 300-800sq to be completed in 10 stages. Stage one has been completed with stage two currently under construction.

Services:

Completed works stage 1

  • 120,000m3 cut to fill completed under AS 3798 level one requirements
  • Compaction control testing to BCC specifications for 3000m of PE sewer, 1613m of stormwater pipe and 1441m of PE watermain
  • Geotechnical investigations for design parameters for 6,245m2 of retaining walls
  • Consolidation Settlement Assessments
  • Geotechnical stability assessments